|


Post
Cards from 1907 of the original Water Street Pumping Station
1870:
The City of Jackson Common Council chartered the Jackson City Water
Company by issuing $100,000 in capital stock. On February 7th
citizens gathered in response to a proclamation issued by Mayor W.M.
Bennett to authorize the city to subscribe to the stock of the newly
organized company of which the city took over $99,750 of the capital
stock. It is not known to this day who owns the other 250 shares.
It was resolved
that the newly formed Water Company secure the construction of the Holly
System of water works in the shortest possible time and contract for the
proper machinery and five miles of pipe. The boiler and engine were
purchased for $40,000. The community was very proud of this machinery.
The pump had a capacity of 1.5 million gallons per day and Jackson's
first water supply was the millpond located along the eastside of Water
Street. It was further resolved that the new Water Company procure a
proper location and plans for a plain brick engine house with a Mansard
roof.
According to the
first chief engineer (Charles H. Christopher) a cofferdam and filter bed
were built out to the middle of the millpond (Grand River). This system
proved to be a total failure because the water was considered unfit to
drink and very little was used. People complained that frogs and
pollywogs were being pumped into their homes.
The first
pumping station was constructed on somewhat of an island at the edge of
the millpond with water all around it. During the first winter all
water mains froze because they had not been installed deep enough to
protect them from the frost. Fires were built on top of the mains in an
attempt to thaw them out. The next year all previously installed water
mains were re-installed at a greater depth.
Attached to the
end of this document are copies of the Proclamation and resolutions that
lead to the development of the Jackson City Water Company.
1874:
The first well was drilled, followed shortly by a second well and the
water works began filtering the river water to improve water quality.
The wells were free flowing and only required a gravity flow to the
pumping station.
1876:
Mr. Charles H. Christopher was appointed the first Chief Engineer of the
Jackson Water Works.
1885:
The first pumping station was completed on Water Street, approximately
where the Water Department’s maintenance garage is located today. A
Holly-Gaskill pump was also installed that year. This was a steam
driven pump with a cross compound, crank and flywheel that could pump
6.0 million gallons of water per day.
1889:
Dependence on river water had decreased and the only river water used
was for a period of 2 hours and 50 minutes for fires. Eventually the
city had 15 free flowing wells along Water and Hamburg Streets and
ceased to use river water all together. 17,200 feet of water main was
also installed at this time.

Early photograph of the Water Street pumping station.

Photograph
of the Water Street Pumping Station taken several years later.

Early photograph of the Water Street Pumping Station in the winter

Inside
the Water Street Pumping Station
1893:
A second and larger Holly-Gasksill pump was installed. This was also a
steam driven pump with a cross compound crank and flywheel that could
pump 10 million gallons of water per day

6 and
10 mg Holly-Gaskill Pumps
1896:
The system of flowing wells on Water Street could no longer meet city
demand. This led to the installation of the Bacon airlift system. This
was a process by which air was injected into the ground and used the
escaping air to lift water to the surface. This increased capacity by
2.5 million gallons per day. The air lift system was only used for four
years and abandoned in 1900 when a suction pump was installed on the
well system to increase supply. The average daily pumpage in 1896 was
2.1 million gallons per day.

Bacon
Air Lift Pump
1904:
The city started metering water to about 23% of its customers who were
billed by consumption. The remainder of customers continued on with the
Water Tax system.
1907:
Some customers were still on semi-annual water tax system based on the
number of fixtures a customer had. A custom with a single faucet paid
an annual cost of $4.

1907
Water Bill paid semi-annually
1913:
The Jackson City Water Works installed a new Snow cross compound pump
with a capacity of 6.0 million gallons per day. 92.5% of all customers
were metered and the average daily pumpage was 2.7 million gallons per
day. The population of the city at that time was 37,316.
In 1913, a
schoolgirl named Hazel, wrote a letter to her grandfather who worked for
the Jackson Water Works wanting to know how many wells the Water Works
had. He gave the following information to her:
There are 15
wells, 4 - 8-inch in diameter, 7 - 10 inch in diameter and 4 - 12 inch
in diameter. They all have a depth of about 250 feet and three are
located on the Water Works grounds while the rest were located on Water
Street south of the Pumping Station for about 3/4 of a mile. All wells
discharged into a 24-inch influent line that discharged into a 25 ft. x
26 ft. settling well from which water is pumped to city customers.

6 mg
Snow Pump
1916:
A ground storage reservoir was constructed just north of the Water
Street pumping station. The reservoir had a capacity of 500,000 gallons
for improved fire protection. This reservoir was used until around 1925
when a new pumping station and underground reservoir were constructed on
Mansion Street. This old reservoir, minus its roof that was removed in
the early 70's, is still standing and is used for storage today.
1917:
Population was nearing 50,000 and daily pumpage was averaging 3.7
million gallons per day. Jackson drilled 4 - 12 inch wells and
constructed a small pump house, called the Belden Road low lift station,
on the city farm south of the Water Street pumping station. Water was
pumped from the wells by the low lift station to the reservoir on Water
Street through a 20" wooden water main. The main was constructed of
wood because of the shortage of cast iron during World War I. The
purpose of this new well field was to replace the older system of wells
on Water Street because they were failing to meet the needs of the city.
The new wells are over 300 feet deep with pumps positioned at the
120-foot level.
The City Farm
became known as the Mansion Street well field that is still in use and
capable of supplying the city with 18 million gallons of water per day.
The low lift station is no longer used as a pump house but is used to
house the No. 1 well and the electrical switches for the well field.
This building received extensive renovation in 2001 and is now referred
to as the "low service building".
1919:
The city Water Works began feeding chlorine to the water supply for
disinfection purposes. The distribution system consisted of 111 miles
of water main and 867 fire hydrants. 28,145 feet of water main was
installed that year and the annual demand was 1,500 million gallons of
water.
1922:
Mr. Charles
H. Christopher retired after 43 years as the Chief Engineer for the
Jackson Water Works. Mr. Christopher came to Jackson in 1865 and joined
the Fire Department in 1868. He remained a member of the Fire
Department for 8 years and was the captain of No. 1 Fire Station the
last 2 years.
On July 2, 1876
Mr. Christopher was appointed Chief Engineer and held that position
until May 1, 1891 when he resigned and became a plant manager for the
Jackson Gas Company for 3 years. He was persuaded by the Board of
Public Works to return as Chief Engineer, which he did and held that
position again until 1922.
The city grew
from a population of 18,000 in 1876 when Mr. Christopher was hired to
50,000 in 1922 when he retired. The Water Street Pumping Station at
the time of his retirement had 3 pumps (6, 8, & 10 mgd capacity) and
four boilers.
Mr. Christopher
believed the Water Street Pumping Station was vulnerable because of its
location to oil storage tanks across the street. He knew that a fire or
explosion could potentially destroy the pumping and disrupt the city's
water supply. He was in favor of constructing a new pumping station on
the city farm south of the Water Street Location. This area was already
being developed as our present day well field and a pumping station were
eventually constructed there.
Mr. Christopher
deplored the use of the wooden water main to move water from the low
lift station to the Water Street Pumping Station. His contention was
that when the wooden main was not used, ground water would seep into it
making any water pumped through it unfit for consumption. Therefore,
the wooden line had to be thoroughly flushed each time it was used and
that wasted a day’s supply of water. He blamed the wood main for a
previous interruption to the city's water supply and said it would not
have happened if it was iron.
An interesting
side note is that Charles Christopher had an impact on the Water Works
Company that extended well beyond his retirement. Descendants and
relatives of Mr. Christopher have always worked for the City Water
Department even until this day. The supervisor of the Jackson City
Water Treatment Plant is related to Mr. Christopher.
1923:
The city authorized $400,000 in bonds for the construction of a new
pumping station on Mansion Street. Construction was started that year
and included 6 wells and a 3.0 million-gallon reservoir.
1925:
In November, construction was completed on the new pumping station and 3
million-gallon underground reservoir. The Water Street pumping station
and reservoir would no longer be used and the pumping station eventually
was demolished. The new pumping station is still in operation today.

Arial
photograph of the Pumping Station on Mansion Street
(probably taken in the early to mid 30's)
There were plans
to move the 6 mg Snow pump installed in the old pumping station on Water
Street in 1913 to the new station on Mansion Street; however, there was
insufficient clearance and the pump was never installed.
The pump was sold and it was later learned that the bonds for
the purchase of the pump had not been paid off and the sale was illegal.
The pump was eventually sold to a city in Indiana.

A
picture of the interior of the Mansion Street Pumping Station probably
taken in the 20's. Note the base in the foreground for the Snow Pump
that was never installed.
1932:
The present day water office and distribution garage were constructed on
the site of the old Water Street pumping station.

Pouring a lead joint to fix a large water main break on Belden Road
(photograph probably taken in the late 30's or early 40's)

Mansion Street Pumping Station (early 50's )
1951: On August 16th the City of Jackson
began adding fluoride to the water supply to promote dental health.

Demolition of the smoke stack at the Mansion Street pumping station.
(Boilers were no longer used to generate steam for pumping)
1954-5:
Two 1.5 million gallon elevated storage reservoirs were constructed and
a 1125 KVA standby generator was installed at the pumping station.

West
Elevated Storage Reservoir under construction
(West
Ave. and North Street)

East
elevated storage reservoir under construction
(Roberts and Tyson Streets)
1961:
A booster pump was installed at Brighton and West Avenue and check
valves installed around the Essex Heights area to form a pressure
district for customers living at the higher elevations in the Essex
Heights area.
1967:
The City of Jackson Water Department completed installation of 130
remote meter reading devices as a pilot program. The remote devices
were called "ARB" which is short for Automatic Reading and Billing.
The devices were manufactured for the Trident Meter and employed a 14
wire and pin contact system to a hand held reader.
1968: A six-month occurrence of bacterial
contamination spurs interest for a water treatment plant.
1970: The City of Jackson and Blackman Township
signed a Water Service Agreement and the east and west transmission
mains were installed.
1971:
A 7.5 million gallon ground storage reservoir was constructed just east
of the pumping station on Mansion Street and the old underground storage
reservoir was no longer used.

Construction of the 7.5 mg ground storage reservoir
(view
from inside the reservoir)

Construction of the 7.5 mg ground storage reservoir
(view
from outside the reservoir)
1974:
The Federal Safe Drinking Water Act became effective, bringing about
many changes and improvements in community water supplies.
1975:
Ground breaking for the new Water Treatment Plant and by city ordinance
the Water Department was delegated responsibility for cross connection
control.
1977:
Jackson
completed construction on its new 24-mgd water treatment plant. The
plant uses a lime and soda ash softening process to lower the total
hardness from approximately 470 ppm to 140 ppm.

Jackson Water Treatment Plant
1977-78:
A severe winter caused many problems with frozen service lines and water
mains.
1978:
Sewer separation project had a major impact on water utility.
1980:
First water treatment sludge removal contract.
1982:
Volatile Organic Compounds (VOC) found in the City's wellfield requiring
quarterly sampling and analysis by the Michigan Department Of Public
Health.
1984:
First city personal computer installed at the Water Treatment Plant.
1986:
A new storage building was added to the Water Street facilities and hand
held computers were first used by Jackson meter readers to read meters.
1984:
The Jackson City Water Department began a program to install Sensus TTR
remote reading devices on residential and some commercial accounts.
This program was accelerated in 1986 and completed around 1992. In the
middle of the process the city switched from the TTR (Tele Tape Remote)
to the ECR (Electronic Communication Register) remote system which is in
use today.
1988:
Water Department publishes "Lead Notice"
Last
of high efficiency well motor replacements
USEPA
proposes new lead rules
1989:
Water main replaced on Cooper Street - Armory Court to Monroe Street
Variable speed drive added at Water Treatment Plant
1990:
Engineering and financial planing begins for a new wellfield.
1992:
Construction of the new well field in Sharp Park and transmission line
to the water treatment plant. Installation of the computerized
control system for the water treatment plant.
1996:
In December of 1996 saw the completion of a Master Plan Study for the
Jackson City Water Department outlining and recommending improvements to
make the water supply infrastructure more reliable.
1997-98:
Both the east and west elevated storage reservoirs were painted. This
involved completely encapsulating each tank to remove the lead base
primer. Area wide contest was held for community input into designs for
tank painting.
1999:
The Jackson City Water Department begins a program to replace old and
undersized water mains and begins a major capital improvement project to
the Water Treatment and pumping facilities on Mansion Street.
2000:
The City of Jackson Water Department enters into a cooperative agreement
with other water suppliers in Jackson County to conduct a Well Head
Protection study for the entire county. This effort will help protect
the aquifer from which everyone obtains drinking water.
A capital
improvement project for the water treatment and pumping facilities is
completed. This project was based on recommendations from the 1996
Master Plan Study. This project was funded with the sale of bonds in
1999. Following is a list of some of the upgrades to water department
facilities:
·
Installed new filter media
·
Installed a new standby diesel generator
·
Installed new electrical switch gear with a grounded system
·
Installed a chlorine scrubber building (Neutralize chlorine gas)
·
Installed new underground power supply to the treatment plant
·
Installed a new dome roof on the ground storage reservoir
·
Replaced old (PCB) transformers
·
Installed new well field switch gear in low service
·
Renovated the low service building
·
Replaced leaking influent and effluent valves within the facilities
·
Replaced the discharge piping for High Service pump #5
·
Replaced electrical disconnects in the filter pipe galley
·
Insulated all piping in the filter pipe galley to reduce moisture
condensation
·
Install additional clean-outs on the decant lines from the lagoons
·
Waterproofed the exterior of the water treatment plant
·
Made exterior repairs to the pumping station.
·
Replaced dust collectors for the lime and soda ash storage bins.

New
dome roof installation on the 7.5 mg ground storage reservoir
2001:
Renovations to low service building are completed and the City Fire
Department completes a program to flow test every fire hydrant in the
city. All black iron potable piping in the water treatment plant was
replaced with new copper lines.
2002:
The City of Jackson Water Department continues its program to replace
old and undersized water mains. This effort will continue until water
service has improved to all areas of the city. This effort will take
several years to complete. Following is a list of streets where the
water mains have been replaced under this program:
98/99:
Street From To
Fourth St.
Michigan Washington
Wilkins First Blackstone
Biddle
Third Blackstone
Fifth
St. Franklin mid-block
99/00:
Pearl St. Blackstone
Mechanic
Kent Robinson Euclid
Kent Addison South St.
East
Argyle Cooper N. East
Frost St.
Cooper end of Frost
James
R Waterloo end of James R
North St.
Lansing Blackstone
Scott Argyle End of Scott
Seymour Ganson Floral
Waterloo
Leroy Argyle
Webb West Steward
E.
High Airline RR tracks
Bridge RR tracks Locust
Newton St.
Porter end of Newton
Montgomery
Blackstone John
00/01:
Commonwealth Clinton
Lansing
Sparks
Clinton Lansing
St.
Clair Clinton Lansing
Morris Sparks Commonwealth
Mason Blackstone First
Elm North St. Blake
WATER
DEPARTMENT SUPERINTENDENTS
Name
From To
Charles H.
Christopher, Chief Engineer 7/2/1876 1922
August Wetzel,
Chief Engineer 1917 Unknown
Donald M.
Hatch 1925
Unknown
David J.
Stelingworth 1932
10/1/56
Chief
Engineer/Superintendent
(Water Pumping)
Everett D.
Cattell, Superintendent 8/28/36 3/9/48
(Water
Distribution)
Joseph M.
Rogeven
5/18/48 2/1/67
Walter J.
Vaclavik 3/6/67
1/6/69
John E.
Tucker
6/17/69 9/25/74
Lawrence E.
Everett
1/6/75 7/2/93
Joseph Michalsky
7/1/93 7/1/95
Richard
Saltzgaber 2/12/96
7/5/02
Glenn Chinavare
7/1/02
Copies
of Historical Documents
Proclamation and Resolution establishing the "Jackson City Water
Company"

Proclamation calling for a meeting of the Common Council to consider
authorization to subscribe to the stock for the Jackson City Water
Company.

Excerpts
from the 1919 Annual Report






|