Sign up for weekly construction update emails below. Emails are sent out weekly during construction season. Weekly emails will begin the week of May 1, when the construction season begins in earnest. At the bottom of this page is a table that shows the status of construction projects slated for the 2017 season.


Subscribe to our mailing list

* indicates required

Street Construction Status - 2017

Location Start
Date
Water
Main
Sewer Curb Sidewalk
Base
Course
Top
Course
Finish
Date
Michigan Ave.
Brown-Steward
April 24
80%
10%
0%
0%
0%
0%
Nov. 2
Washington Ave.
& Glick Highway
April 24
-
-
0%
0%
0%
0%
Dec. 8
RR Crossing
Michigan/Cooper
Oct. 1
-
-
0%
0%
0%
0%
Dec. 8
Glick Highway
Water Main
July 10
0%
-
0%
0%
-
0%
Aug. 18
E. Michigan Ave.
Cooper-Dwight
April 17
-
-
100%
100%
-
100%
June 17
N. West Ave.
North-Boardman
Aug. 14
-
-
-
-
0%
0%
Sept. 29
PAKA Connector 
Trail
May 2
-
100%
0%
70%
90%
0%
July 14
Kibby Road
Limits-West Ave.
Sept. 10
0%
0%
0%
0%
0%
0%
Nov. 15
Parking Lot 20
Expansion
Mar. 13
-
90%
0%
0%
0%
0%
Nov. 15
Glick Highway
LIghting/Parking
July 10
-
-
-
-
-
-
Sept. 29
Blackstone St.
Lighting
July 10
-
-
-
-
-
-
Sept. 29
Parking Lot 6
Sealcoating
July 10
-
-
-
-
-
0%
June 25
Parking Lot 7
Repaving
July 10
-
0%
0%
0%
0%
0%
July 21
Alleyway
Washington/Cortland
Aug. 7
-
-
0%
-
0%
0%
June 30
Alleyway
Wesley/Washington
July 19
-
0%
0%
0%
-
0%
June 30
First Street
Franklin-Washington
July 31
-
0%
0%
0%
0%
0%
Sept. 29
Jackson Street
Franklin-Washington
July 31
0%
0%
0%
0%
0%
0%
Oct. 20
Cortland Street
First-Blackstone
Aug. 14
0%
-
0%
0%
0%
0%
Sept. 29
Michigan Ave.
First-Blackstone
Aug. 28
0%
0%
0%
0%
0%
0%
Oct. 20
Steward Ave.
Water Main
Sept. 11
0%
-
0%
0%
0%
0%
Oct. 20
Dewey Ave.
Clinton-Lansing
Sept. 25
0%
-
0%
0%
0%
0%
Nov. 3
Fleming
Maguire-Blakely
Oct. 9
0%
-
0%
0%
0%
0%
Nov. 3
Preventive Work
Various Streets
Sept. 5
-
-
-
-
-
0%
Sept. 29