DigJacksonheader
The City of Jackson's "Dig Jackson" email list is used to update those interested in street construction projects in the City.

Sign up for weekly construction update emails below. Emails are sent out weekly during construction season. Weekly emails will begin the week of May 1, when the construction season begins in earnest. At the bottom of this page is a table that shows the status of construction projects slated for the 2017 season.


Subscribe to our mailing list

* indicates required

Street Construction Status - 2017

Location Start
Date
Water
Main
Sewer Curb Sidewalk
Base
Course
Top
Course
Finish
Date
Michigan Ave.
Brown-Steward
April 24
90%
50%
0%
0%
0%
0%
Nov. 2
Washington Ave.
& Glick Highway
April 24
-
-
0%
0%
0%
0%
Dec. 8
RR Crossing
Michigan/Cooper
Oct. 1
-
-
0%
0%
0%
0%
Dec. 8
Glick Highway
Water Main
Aug. 14
0%
-
0%
0%
-
0%
Sept. 18
E. Michigan Ave.
Cooper-Dwight
April 17
-
-
100%
100%
-
100%
June 17
N. West Ave.
North-Boardman
July 19
-
-
-
-
0%
0%
Aug. 18
PAKA Connector 
Trail
May 2
-
100%
0%
100%
100%
100%
July 7
Kibby Road
Limits-West Ave.
Sept. 10
0%
0%
0%
0%
0%
0%
Nov. 15
Parking Lot 20
Expansion
Mar. 13
-
90%
0%
0%
0%
0%
Nov. 15
Glick Highway
LIghting/Parking
July 10
-
-
-
-
-
-
Sept. 29
Blackstone St.
Lighting
July 10
-
-
-
-
-
-
Sept. 29
Parking Lot 6
Sealcoating
July 6
-
-
-
-
-
0%
July 7
Parking Lot 7
Repaving
Sept. 18
-
0%
0%
0%
0%
0%
Oct. 27
Alleyway
Washington/Cortland
Aug. 7
-
-
0%
-
0%
0%
Aug. 25
Alleyway
Wesley/Washington
June 12
-
100%
100%
100%
-
100%
June 29
First Street
Franklin-Washington
Sept. 18
-
0%
0%
0%
0%
0%
Sept. 29
Jackson Street
Franklin-Washington
Sept. 18
0%
0%
0%
0%
0%
0%
Nov. 10
Cortland Street
First-Blackstone
Sept. 18
0%
-
0%
0%
0%
0%
Nov. 10
Michigan Ave.
First-Blackstone
Sept. 18
0%
0%
0%
0%
0%
0%
Nov. 10
Steward Ave.
Water Main
Sept. 18
0%
-
0%
0%
0%
0%
Nov. 10
Dewey Ave.
Clinton-Lansing
Sept. 18
0%
-
0%
0%
0%
0%
Nov. 10
Fleming
Maguire-Blakely
Sept. 18
0%
-
0%
0%
0%
0%
Nov. 10
Preventive Work
Various Streets
Sept. 18
-
-
-
-
-
0%
Nov. 10